Control room scope matrix: GC, integrator and owner responsibilities.

For owners, owner’s representatives, design teams and integrators assigning scope on a control room or operations center.

Highlands Construction · November 2026

Control-room projects divide design, supply, installation, integration and acceptance responsibilities among several parties: the owner, the design team, one or more specialist integrators and the general contractor. Scope gaps can arise at the interfaces between them.

The matrix below is a starting point for assigning responsibilities before pricing. Use it to ask the right questions, then record the actual assignments in the contract documents for your project.

Responsibility matrix

ItemTypically designed byTypically furnished and installed byGC usually providesCommon scope gap
Room layout and sightlinesArchitect or control-room consultant, with integrator input—Builds to the approved layout; coordinates walls, doors, columns and ceilingsConsole clearances and sightlines not checked against doors, columns or ceiling elements
ConsolesConsole manufacturer, from the approved layoutIntegrator or console manufacturerFloor preparation, backing where required, power and data stubs at the agreed locationsFloor flatness, floor loading and stub locations not agreed before slab or floor work
Video wall and displaysIntegrator for AV requirements; responsible structural designer for supports and anchorageIntegratorStructural backing, power, pathways, ventilation and service access as detailedBacking, mounting and service-access details missing from the construction documents
Power distributionElectrical engineer of recordElectrical subcontractor under the GCDistribution, circuits and connections shown in the construction documentsCircuit requirements for consoles and racks arriving after electrical design is complete
UPS and backup powerElectrical engineer of recordSupply, installation, connections and startup assigned separately among the owner, contractors and equipment vendorInstallation and connections as assignedWho furnishes, sets, connects and starts up owner-furnished equipment
CoolingMechanical engineer of recordMechanical subcontractor under the GCEquipment, ductwork and controls shown in the construction documentsEquipment heat loads and operating hours confirmed too late for mechanical design
Low-voltage cablingDesign team or integratorVaries: integrator or low-voltage contractorPathways, sleeves, backboxes and penetrations as assignedWho pulls, terminates, labels and tests each cable type
Access control and securitySecurity designer or integratorSecurity integratorDoor hardware coordination, backboxes, conduit and power as assignedDoor hardware and access-control devices specified by different parties without coordination
IT and network equipmentOwner’s IT team and relevant integrators, with network architecture and security requirements approved by the ownerOwner, integrator or IT contractor, as assigned; distinguish equipment supply, physical installation, configuration and network connectionRack locations, power, grounding, cooling and pathways as designedRack delivery timing and installation access not tied to the construction schedule
Lighting and controlsDesign teamElectrical subcontractor under the GCFixtures, dimming and controls shown in the construction documentsDimming or scene control expected to integrate with room systems without a defined interface
Acoustic treatmentsDesign team or acoustic consultantSubcontractor under the GCInstallation of specified treatmentsTreatments assumed in the layout but not specified in the documents
Fire protection and life safetyFire protection engineer and design teamAssigned fire-suppression, fire-alarm, electrical and controls contractorsSystems shown in the construction documents; coordination with HVAC and power shutdownsInterfaces between fire alarm, HVAC shutdown and critical equipment not defined
Controls and cross-system integrationRelevant designers and specialist integratorsAssigned controls, AV, security and network providersSpecified building interfaces and coordination of contracted tradesPoint lists, protocols, programming, licenses and end-to-end interface testing not assigned
Owner-furnished equipment logisticsEquipment supplier’s handling and storage requirementsDelivery, offloading, receiving, storage and preservation assigned separatelyOnly the logistics, protection and records assigned to itDamage responsibility, storage conditions and warranty obligations unallocated
Testing and acceptanceCommissioning plan from the owner or commissioning authorityContractors and vendors perform assigned tests; commissioning oversight, witnessing, integrated testing and acceptance responsibilities are established in the owner-approved planPerforms assigned testing, coordinates contracted trades’ participation, resolves deficiencies within its scope and provides required recordsIntegrated test procedures, prerequisites, participation, retesting and acceptance authority not assigned
Training and turnoverOwner defines requirementsTraining and documentation assigned by system to the relevant installer, integrator, vendor or other contracted providerConstruction records, warranties and O&M documents for contracted scopeOperator training for integrator systems assumed to be the GC’s responsibility

“Typically” describes a common arrangement, not a rule. Assignments vary by owner, project delivery method and contract.

How to use it

  • Add a column for each party on your project and mark who designs, furnishes, installs, connects, tests and accepts each item
  • Before pricing, assign known responsibilities and document open decisions, assumptions, allowances and exclusions
  • Incorporate the agreed matrix into procurement and contract documents so every bidder prices the same scope
  • Update it whenever equipment, scope or responsible parties change
  • For utility control houses, add project-specific rows for protection and control panels, station AC/DC supplies and batteries, grounding, and cable-entry interfaces
  • Revisit it when the integrator is selected, since integrators differ in what they furnish and install

For the questions to settle before pricing, see the control room construction checklist.

For construction scope and delivery discussions, see our control room and operations center construction services.